The Avery — completed mixed-use development, Brooklyn

The Avery — Mixed-Use, Brooklyn

A 320,000 sq ft mixed-use scheme combining 184 residential units, 28,000 sq ft of street-level retail, and a public courtyard tying two formerly disconnected blocks together. Delivered May 2025.

The brief

A development that had to feel like the neighbourhood, not impose on it

The client — a Brooklyn-based developer with three previous projects in the borough — came to us with a permitted scheme and a problem. The original GC had walked at week 14 over a structural-steel cost dispute, and the design team's drawings still had open coordination flags around the podium-deck transfer.

We took on the project as design-build, picked up the design coordination through our in-house engineering team, and re-tendered the steel package within six weeks. The client's original delivery date held — but only because we wrote the schedule from the bottom up rather than inheriting the previous team's plan.

Site progress, Q3 2024
The Avery, by the numbers

A 22-month delivery, end to end

  • 320,000 sq ft Total floor area

    184 residential + 12 retail + courtyard

  • 0 mo On site

    Recovery schedule, hit on day one

  • $1.8m Returned to client

    Open-book savings vs GMP

  • 0 Recordable incidents

    Across 320,000 site-hours

Challenges

A site with no margin for error

The site sat between two occupied buildings with party walls dating to 1908. Foundation work required underpinning a six-storey neighbour while keeping its tenants in occupation. Two of those tenants ran ground-floor businesses where vibration would have stopped trade.

We worked with a vibration-monitoring specialist to install real-time sensors before any pile work started, set thresholds 40% below code minimum, and built the schedule around windows when the affected businesses were closed. Zero claims, zero downtime for the neighbours, zero programme slippage.

Underpinning works on the party wall
Approach

Self-perform concrete, modular MEP

We self-performed the structural concrete — slab on grade through level 14 — using a single tower crane and a 28-day pour cycle that gave the steel and facade trades predictable hand-offs. The MEP risers were pre-fabricated off-site in 12-foot modules, lifted into place during the night-shift window, and connected with quick-disconnect fittings. That alone saved 47 site days.

The podium-deck transfer — the hand-off point that derailed the previous team — was redesigned as a hybrid steel-concrete composite truss. We tendered and built it in eight weeks, ten days ahead of the redrawn schedule.

Modular MEP riser being craned into position
Recovery takeover

Week 14 condition vs. handover

Drag to compare the site as we found it — abandoned by the original GC mid-pour — with the completed Bedford Avenue elevation 22 months later.

The Avery — completed Bedford Avenue elevation Handover
Avery site at week 14 — recovery takeover condition Week 14
Results

Delivered on the original date, $1.8m under final budget

Substantial completion was issued 11 days ahead of the recovery schedule, matching the developer's original target despite the 14-week delay we inherited. Final cost was $1.8m under the contracted GMP, with the savings returned to the client per our open-book agreement.

184 units leased within 90 days of TCO. The retail spaces were fully signed before practical completion. The public courtyard — a contractual community-amenity requirement — has become a regular venue for the Bedford-Stuyvesant Restoration Corporation's summer programming.

DISCUSS YOUR PROJECT
Public courtyard, post-completion
In their words

“Meridian Build inherited a project that was 14 weeks behind, with our original GC walked off site and a half-poured podium deck nobody wanted to claim. They ran a 30-day audit, rewrote the schedule from the bottom up, and brought the building in on the original handover date — $1.8m under our GMP. Eleven years and four projects later, they're still our default choice.”

Robert Chen
Robert Chen Managing Partner · Bedford-Stuyvesant Development Partners
Project facts

The Avery, by the numbers

  • Client

    Bedford-Stuyvesant Development Partners

  • Location

    Brooklyn, NY

  • Sector

    Mixed-use residential + retail

  • Floor area

    320,000 sq ft

  • Units

    184 residential, 12 retail

  • Procurement

    Design-build (rescue takeover)

  • Programme

    22 months on site

  • Completed

    May 2025

Working on something similar?

Bring the brief, even if it's already in motion.

Roughly a fifth of our work is rescue or takeover. If your project needs a fresh team, we'll tell you within a week whether we're the right fit.