How modular framing cut six weeks off our latest mid-rise build
All articles May 3, 2026 4:30:01 PM · Studio Nope

How modular framing cut six weeks off our latest mid-rise build

1 min read

When the team broke ground on Westmount Avenue last spring, we set ourselves an unusual target: deliver the structural shell six weeks ahead of a comparable stick-built project. Here is how modular framing got us there.

Choosing a modular partner

We evaluated four prefabricators on tolerances, freight logistics, and on-site crane sequencing. The winner was the team that gave us the most honest answers about what could go wrong, not the team with the glossiest deck.

Tolerances matter

The hardest lesson was that 6mm of accumulated tolerance per floor compounds quickly. We rebuilt our QA process around laser scans of every level before the next module landed.